1.Which of the following is NOT a characteristic of the pure projectized organizational structure?
a. There is a lack of opportunity for technical interchange between projects.
b. There may be d...

1.Which of the following is NOT a characteristic of the pure projectized organizational structure?
a. There is a lack of opportunity for technical interchange between projects.
b. There may be duplication of facilities and an inefficient use of resources.
c. There is a complete line of authority over the project.
d. Limited span of control.

2.Which form of power is the MOST effective in terms of the project manager influencing upper management?
a. Formal power
b. Reward power
c. Penalty power
d. Referent power

3.Cost plus Percentage of Cost (CPPC) contracts provide:
a. reimbursement of allowable cost of services performed plus an agreed upon percentage of the cost as profit.
b. reimbursement of allowable costs plus a fixed fee which is paid proportionately as the contract progresses.
c. the supplier with a fixed price for delivered performance plus a predetermined fee for superior performance.
d. reimbursement of cost according to the amount of time and consumables used.

4.If a bidder lost a contract proposal, what is a course of action, which can be taken to seek a remedy?
a. Sue the buyer for damages.
b. Protest the outcome of the bid award.
c. Seek to dispute the credentials of the winning bidder.
d. Issue a statement to the press discussing the unfairness to the bidding selection process.

5.Reserve funds are set aside for use when:
a. an up-scope of the project requires additional funds to compensate the initial budget.
b. they are needed for the sporadic fluctuation in potential labor rates when a union contract is under negotiation.
c. anticipated problems have been identified but not completely expected.
d. a fund used when the client requests an up-scope for the project.


上期答案: 1. [b] 2. [b] 3. [b] 4. [e] 5. [f]


PMP考试样题第三期

1.Which of the following functions does NOT pertain to the roles and responsibilities of the project manager?
a. Planning
b. Staffing
c. Controlling
d. Directing

2.In a project that has never been done before, the project manager must select one or more methods of estimating task duration. What is the most reliable method under this described situation?
a. Historical data
b. Expert judgment
c. Parametric learning curves
d. Estimating manuals

3.The engineer of a project is participating in the planning phase and makes a significant contribution to the technical scope. This an example of what type of skill and knowledge?
a. Inherent
b. Stakeholder
c. Technical evaluation
d. Convergent thinking

4.In a communication message, the receiver is the one who accepts the message and interprets it while the sender is the one who the message.
a. rejects
b. carriers
c. accepts
d. forwards
e. originates

5.Which of the following can cause a communication barrier?
a. Differing perceptions as to project goals and objectives
b. Insufficient action on the part of the project manager
c. Competition for facilities, equipment, material, manpower, and other resources
d. Personality conflicts between managers and / or other personnel
e. Resistance to change
f. All of the above

上期答案: 1. [b] 2. [e] 3. [e] 4. [c] 5. [d]



其它培训参考信息:
PMP全球查分系统
我的PMP备考心得 下
我的PMP备考心得 上
2个多月的PMP备考历程 2
2个多月的PMP备考历程 1
我的PMP之路
PMP备考心得
PMP考试的几点体会



信息来自互联网,敬请核实,谨慎使用



 





Jobs in Other Countries

  中国 | Worldwide: United States United Kingdom Australia Canada India | Travel AgencyASKEDU.com